Hello,
I create links from items in a source module to items in a target module. I use the suspect links to analyze the impacts in the target module when the items in the source module are modified. But, the source module has had many baselines and the suspect links are cleared with the text (Analysis Menu -> Suspect links -> Display All changes -> In-links (open modules only)):
"The module was baselined on 26/4/2013 11:18:09 and this has affected the history. There may be entries in the baseline describing the changes that made the link suspect."
Is there some way to not clear the suspect links when the source module creates a new baseline?
Regards.
Thrego - Thu May 16 07:45:25 EDT 2013 |